New Years Resolution (Model Railroad Related)

January 8, 2009

I resolve to spend at minimum 10 hours working on things that will lead towards the successful creation and operation of my Reading Company Layout.

I also resolve to post a weekly wrap up of the activities that I have done which lead me towards the goal.

New Year 2009

January 8, 2009

Happy New Year to everyone out there which has been visiting my slow attempts at getting my layout built.

I have worked out a schedule that I plan to keep up in order to get something built up and running this year.

Here is the new planned schedule:

End of January – Finish Layout Plan, get reviews and improvements, and clean out and organize the junk that’s in the layout space.

February – Build the walls and wire the layout space.  Also install some sort of flooring system, maybe carpet or foam panels

March to June -Benchwork construction, and track work in some areas.